NOTICE OF UPCOMING WORK AND TRAFFIC IMPACTS

This notice regards temporary traffic impacts for the above project for paving on N Reed Street and Portobello Ave and sidewalk and curb ramp work at various locations.

The 2024 Pavement and Pedestrian Improvements Project consists of preparing N Reed Street between SR 20 and Sapp Road for a full width asphalt overlay and preparing Portobello Avenue for a full width asphalt overlay between N Fruitdale Road and East Gateway Heights Loop. The preparation work on both roads will include curb ramp removal and replacements and grinding the existing asphalt along the curb lines before placing a 2-inch lift of asphalt.

In addition to the roadway paving, the project includes installing a sidewalk on the north side of State Street between Central Street and the Senior Center along with curb ramp improvements, replacing the sidewalk on the south side of Nelson Street between 6th and 7th Streets along with curb ramp improvements, and replacing sidewalk sections and curb ramp improvements at various locations in the downtown area.

N REED STREET

N Reed Street will be open to at least one lane of traffic at all times during working hours. There will be access delays during the grinding and paving operations. These delays will be kept to a minimum as much as possible and we will work with you to ensure you are able to get in or out when you need to.

The paving preparation and paving work will impact parking along N Reed Street. In order to perform the grinding work along curbs and the final overlay paving, it will be necessary to have all vehicles cleared from the street while these operations take place.

PORTOBELLO AVENUE

Portobello Avenue will be open to at least one lane of traffic at all times during working hours. There will be access delays during the grinding and paving operations. These delays will be kept to a minimum as much as possible and we will work with you to ensure you are able to get in or out when you need to.

The grinding work will be done before the paving and is anticipated to take only a day for each road. The final paving may take a couple of days as well.

Work is anticipated to start the week of June 17th and be complete by August 30, 2024.

The Contractor for the project, SRV Construction, plans on starting the project with the Nelson Street improvements.

Once the project schedule is in place, we will give advance notice of the upcoming work that will impact access on both roads and when we will need to have N Reed Street cleared of vehicles.

Please feel free to contact David Lee, City Engineer at 360-855-3219 or by email dlee@sedro-woolley.gov  with any questions you might have. 

Para más información del proyecto en español, por favor llame al 360-855-3215